Pullman Moscow Regional Airport Will Pay Nearly $15 Million For The Property And Buildings
The Washington State University Board of Regents has unanimously approved the sale of university-owned land to the Pullman Moscow Regional Airport for $14,772,750. The sale of this property will allow the airport to continue the re-alignment of the airport runway.

The land in question currently houses the WSU’s Terre View Research Facility. The Regents also unanimously approved a motion to relocate the Research Facility at the meeting.
The Pullman Moscow Regional Airport has been planning a re-alignment of its runway to increase width and length of the runway to bring into compliance with FAA regulations. The runway’s new alignment puts the Runway Protection Zone over research facilities owned by the university. In total, work conducted at the research facilities has generated more than $90 million in research funding since 2006.
Programs affected include:
- Intramural U.S. Department of Agriculture research.
- College of Veterinary Medicine research.
- Tukey Orchard.
- Animal Sciences for the College of Agricultural, Human and Natural Resource Sciences.
Upon successful conclusion to negotiations on land acquisition and relocation costs, the university intends to construct and relocate impacted animal research programs and support facilities to Tula Young Hastings Farm, and Tukey Orchard functions to Spillman Farm. Both properties are currently owned by the university. The final settlement amount could vary by up to $300,000 depending on final inventory of special improvements.
The airport prepared an appraisal and relocation study, which determined the fair market value of land to be acquired for the runway realignment program. An offer was presented to WSU in March 2016. WSU prepared an independent appraisal and presented a counter offer to the airport. The airport and the university have since been in negotiations about ways to move the runway project forward while protecting the affected research.
WSU has worked collaboratively with the airport in support of the runway realignment project. WSU provided a temporary construction easement necessary for phase 1 of the project; provided a use permit allowing the airport to construct a haul road on university property; renegotiated a lease with the Department of Transportation whereby WSU voluntarily relinquished a portion of a leasehold to allow for permitting and construction of a haul road; and, most recently, executed an electrical transmission easement in favor of Avista, in order to save the project from significant delay without immediate compensation.
(DOT Image provided with Washington State University news release)
More News
From 2016 (YouTube Edition): The Canadian Forces Snowbirds Can Best Be Described As ‘Elegant’… EAA AirVenture 2016 was a great show and, in no small part, it was>[...]
Airplane Lunged Forward When It Was Stuck From Behind By A Tug That Was Towing An Unoccupied Airliner Analysis: At the conclusion of the air taxi flight, the flight crew were taxii>[...]
Aero Linx: International Stinson Club So you want to buy a Stinson. Well the Stinson is a GREAT value aircraft. The goal of the International Stinson Club is to preserve informatio>[...]
Request Full Route Clearance Used by pilots to request that the entire route of flight be read verbatim in an ATC clearance. Such request should be made to preclude receiving an AT>[...]
"Today's battlefield is adapting rapidly. By teaching our soldiers to understand how drones work and are built, we are giving them the skills to think creatively and apply emerging>[...]