NASA Report Posits Moon Remains Distant | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-07.07.25

Airborne-NextGen-07.08.25

AirborneUnlimited-07.09.25

Airborne-FlightTraining-07.10.25

AirborneUnlimited-07.11.25

Wed, Jun 15, 2022

NASA Report Posits Moon Remains Distant

To Boldly Go—Over Budget

NASA intends to once again land human beings in the moon. The space agency intends, also, to bring Mars within the purview of human exploration.

These lofty and concomitant goals are largely dependent on the ongoing development of the Space Launch System (SLS)—a two-stage, heavy-lift rocket that will launch the Orion Multi-Purpose Crew Vehicle (Orion) into space.

Currently, NASA is developing two mobile launchers at its Kennedy Space Center in Florida. Each massive construct comprises a two-story base structure—the platform to support the SLS vehicle—and a tower equipped with connection lines; launch accessories; and a walkway for personnel, equipment, and astronauts. Once complete, the mobile launchers will facilitate the launch of various iterations of the integrated SLS/Orion system.

Construction of the first mobile launcher (ML-1) was completed in 2010. In 2019, NASA awarded a $383-million contract to Bechtel National, Inc.— the American engineering, procurement, construction, and project management company—to design, build, test, and commission the second mobile launcher (ML-2).

In March 2020, the NASA Office of Inspector General issued a report addressing the ongoing development of both mobile launchers. Subject report examined the extent to which the space agency is meeting cost, schedule, and performance goals for the ML-2 contract. The report brings to light shocking    overruns, and speaks to the inefficiencies, greed, profiteering, and breathtaking ineptitude with which U.S. Governmental programs are afflicted.

To wit.

NASA, by current estimates, will spend 2.5 times ($1-billion) more than initially planned for the ML-2 contract, and take delivery of the completed launcher 2.5 years later than scheduled.

As of May 2022, design work on the ML-2 remained incomplete.

Consequently, Bechtel officials do not expect actual construction of the launcher to begin until the first quarter of fiscal year 2023–at the earliest. When construction does begin, NASA expects unforeseen but inevitable technical challenges to engender further cost increases and delays. 

Once the new launcher is delivered, NASA testing requirements will see its operational debut pushed back to at least November, 2026. 

Compounding Bechtel’s projected cost increases and schedule delays, an ML-2 project analysis provided only a

3.9 percent confidence level that the nearly $1 billion cost and October 2025 delivery estimates were accurate. 

The Office of the Inspector General made a number of suggestions pertaining to better tracking spending, schedules, and keeping NASA and its contractors accountable for overruns, but the reports overall tenor suggested the goal of getting to the Moon by 2024 is no longer possible.

FMI: www.nasa.gov

Advertisement

More News

NTSB Final Report: Aviat A1

Airplane Bounced About 3 Ft Then Touched Back Down And Then, With No Brakes Applied, The Airplane Began Veering To The Left Analysis: The pilot entered the airport traffic pattern >[...]

ANN's Daily Aero-Linx (07.08.25)

Aero Linx: British Microlight Aircraft Association (BMAA) The primary focus within all aviation activity is SAFETY. In all aspects of our sport SAFETY must come first, whether it b>[...]

Classic Aero-TV: Fly Corvair’s Reliable Engine Alternative

From SnF25 (YouTube Edition): William Wynne Builds Practical Aircraft Engines on the Corvair Platform Seeking an affordable alternative to the traditional aircraft engine options, >[...]

ANN FAQ: Contributing To Aero-TV

How To Get A Story On Aero-TV News/Feature Programming How do I submit a story idea or lead to Aero-TV? If you would like to submit a story idea or lead, please contact Jim Campbel>[...]

Classic Aero-TV: CiES Fuel-Quantity and e-Throttle Systems Praised

From 2023 (YouTube Edition): Bridge of CiES CiES Inc. is a Bend, Oregon-based designer and manufacturer of modular embedded aircraft systems and sensors. The company’s fuel-l>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2025 Web Development & Design by Pauli Systems, LC