NASA: First SLS Mission Will Slip To 2019 | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-11.24.25

AirborneNextGen-
11.18.25

Airborne-Unlimited-11.19.25

Airborne-AffordableFlyers-11.20.25

AirborneUnlimited-11.21.25

LIVE MOSAIC Town Hall (Archived): www.airborne-live.net

Tue, May 02, 2017

NASA: First SLS Mission Will Slip To 2019

GAO Finds Technical Challenges Are Leading To More Delays

The Government Accountability Office (GAO) has released a report saying that the first launch of NASA's SLS rocket will likely not happen until sometime in 2019 due to technical challenges with the massive launch system.

According to the report, NASA's three human exploration programs—Orion Multi-Purpose Crew Vehicle (Orion), Space Launch System (SLS), and Exploration Ground Systems (EGS)— are making progress on their respective systems, but the EM-1 launch date is likely unachievable as technical challenges continue to cause schedule delays. 

All three programs face unique challenges in completing development, and each has little to no schedule reserve remaining between now and the EM-1 date, meaning they will have to complete all remaining work with little margin for error for unexpected challenges that may arise. 

The programs all face challenges that may impact their remaining schedule reserve. For instance:

  • the Orion program’s European Service Module is late and is currently driving the program schedule;
  • the SLS program had to stop welding on the core stage—which functions as the SLS’s fuel tank and structural backbone—for months after identifying low weld strengths. Program officials stated that welding resumed in April 2017 following the establishment of a corrective action plan;
  • the EGS program is considering performing concurrent hardware installation and testing, which officials acknowledge would increase complexity; and
  • each program must integrate its own hardware and software individually, after which EGS is responsible for integrating all three programs’ components into one effort at Kennedy Space Center.

The GAO says in the report that low cost reserves further intensify the schedule pressure. Senior NASA officials said they are analyzing the launch schedule and expect that the EM-1 date will have to slip, but they have yet to make a decision on the feasibility of the current date or report on their findings. With budget discussions currently ongoing for fiscal year 2018, the last year prior to launch, Congress does not yet have insight into the feasibility of the EM-1 launch date, or the repercussions that any cost increase or delays could have in terms of cost and schedule impacts for NASA’s entire portfolio. Unless NASA provides Congress with up-to-date information on whether the current EM-1 date is still achievable, as of the time the agency submits its 2018 budget request, both NASA and Congress will continue to be at risk of making decisions based on less than the entire picture and on likely unachievable schedules.

The GAO recommended that NASA should confirm whether the current EM-1 date is still achievable no later than as part of its fiscal year 2018 budget submission, and propose a new, realistic EM-1 launch readiness date, if warranted, and report its findings to Congress. NASA concurred with both recommendations and agreed that EM-1 will be delayed.

(Images from file)

FMI: Full Report 

Advertisement

More News

Classic Aero-TV: Pure Aerial Precision - The Snowbirds at AirVenture 2016

From 2016 (YouTube Edition): The Canadian Forces Snowbirds Can Best Be Described As ‘Elegant’… EAA AirVenture 2016 was a great show and, in no small part, it was>[...]

NTSB Final Report: Costruzioni Aeronautiche Tecna P2012 Traveller

Airplane Lunged Forward When It Was Stuck From Behind By A Tug That Was Towing An Unoccupied Airliner Analysis: At the conclusion of the air taxi flight, the flight crew were taxii>[...]

ANN's Daily Aero-Linx (11.23.25)

Aero Linx: International Stinson Club So you want to buy a Stinson. Well the Stinson is a GREAT value aircraft. The goal of the International Stinson Club is to preserve informatio>[...]

ANN's Daily Aero-Term (11.23.25): Request Full Route Clearance

Request Full Route Clearance Used by pilots to request that the entire route of flight be read verbatim in an ATC clearance. Such request should be made to preclude receiving an AT>[...]

Aero-News: Quote of the Day (11.23.25)

"Today's battlefield is adapting rapidly. By teaching our soldiers to understand how drones work and are built, we are giving them the skills to think creatively and apply emerging>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2025 Web Development & Design by Pauli Systems, LC