Dickson Outlines Steps For 737 MAX Return To Service | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-11.17.25

AirborneNextGen-
11.11.25

Airborne-Unlimited-11.12.25

Airborne-FltTraining-11.13.25

AirborneUnlimited-11.14.25

LIVE MOSAIC Town Hall (Archived): www.airborne-live.net

Fri, Feb 14, 2020

Dickson Outlines Steps For 737 MAX Return To Service

Airliners Have Been Grounded For 11 Months

FAA Administrator Steve Dickson said there is a "waterfall" of actions that need to be completed to return the Boeing 737 MAX to service.

Dickson (pictured) spoke to reporters on the sidelines of the Singapore Air Show this week. He said there is still no firm timetable for recertification of the beleaguered airplane or its return to flight. But he did say certifications flights are coming.

Reuters reports that Dickson said there are multiple steps that will be taken between the certification flights and a return to service, which he estimates will take about a month barring any unforeseen issues that may arise during those flight tests. Individual airline's training plans will also have to be approved by the FAA.

Among the milestones outlined by Dickson were:

  • Certification flight test by FAA pilots to evaluate the compliance of final software, revised following the crashes.
  • Analysis of flight data, expected to take “a few days”.
  • Multi-regulator Joint Operational Evaluation Board (JOEB) simulator exercises to evaluate Boeing’s training proposals. Dickson and his deputy will personally complete the training alongside U.S. and international crews. Takes 9-10 days.
  • An addendum to a Flight Standardization Board (FSB) report, which in turn defines minimum training needs. “It will take a few days to complete that,” Dickson said.
  • The result will be put out to public comment for 15 days.

After final design documentation is prepared and verified, a master Minimum Equipment List will be established after public comments that have been sought since Dec 5.

Eventually, the FAA will publish an AD advising airlines of required corrective actions, and "within a day or two" the FAA would rescind the grounding order that has been in effect since last March. The FAA will then issue airworthiness certificates for each individual airplane.

Some of the tasks will be carried out concurrently, according to Dickson.

(Image from file)

FMI: Source report

Advertisement

More News

ANN's Daily Aero-Term (11.16.25): NonApproach Control Tower

NonApproach Control Tower Authorizes aircraft to land or takeoff at the airport controlled by the tower or to transit the Class D airspace. The primary function of a nonapproach co>[...]

Aero-News: Quote of the Day (11.16.25)

“This shutdown inflicted real damage. Beyond disrupting operations and adding risk into the aviation system… it hindered essential career growth opportunities and stal>[...]

ANN's Daily Aero-Linx (11.16.25)

Aero Linx: The Mooney Mite Site Dedicated to the Mooney M-18 Mite, "The Most Personal Airplane," and to supporting Mite owners everywhere. The Mooney M-18 Mite is a single-place, l>[...]

NTSB Final Report: Vans Aircraft Inc RV-12

Pilot’s Improper Installation Of The Control Stick Pushrod Assemblies, Which Resulted In Separation Of The Left Pushrod And A Total Loss Of Roll Control Analysis: While retur>[...]

ANN FAQ: How Do I Become A News Spy?

We're Everywhere... Thanks To You! Even with the vast resources and incredibly far-reaching scope of the Aero-News Network, every now and then a story that should be reported on sl>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2025 Web Development & Design by Pauli Systems, LC