Lockheed Martin Team Completes Requirements Milestone For GPS IIIB Program | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-11.03.25

AirborneNextGen-
11.04.25

Airborne-Unlimited-11.05.25

Airborne-Unlimited-11.06.25

AirborneUnlimited-10.17.25

Affordable Flying Expo Tickets (Discount Code: AFE2025): CLICK HERE!
LIVE MOSAIC Town Hall, 1800ET, 11.07.25: www.airborne-live.net

Sun, Jun 27, 2010

Lockheed Martin Team Completes Requirements Milestone For GPS IIIB Program

First Launch Planned for 2014

A key requirements review for the Global Positioning System (GPS) IIIB satellite series under the U.S. Air Force's next generation GPS III Space Segment program has been successfully completed, according to contractor Lockheed Martin. The company says GPS III will improve position, navigation and timing services and provide advanced anti-jam capabilities yielding superior system security, accuracy and reliability for users around the globe.

Lockheed Martin Space Systems of Newtown, PA, is working under a $3 billion Development and Production contract to produce up to 12 GPS IIIA satellites, with first launch projected for 2014. The contract, which features a "back to basics" acquisition approach to low-risk constellation sustainment and technology insertion, includes a Capability Insertion Program (CIP) designed to mature technologies and perform rigorous systems engineering for the future IIIB and IIIC increments planned for follow-on procurements.

In a Monday news release, the company says it recently completed a two-day GPS IIIB System Requirements Review (SRR) with the U.S. Air Force at Lockheed Martin's facilities in Valley Forge, PA. Over 170 attendees participated in the SRR, including representatives from the U.S. Air Force's GPS Wing, Air Force Space Command, the Defense Contract Management Agency, the OCX Ground Segment team, the Federal Aviation Administration and user communities.

"The GPS IIIB SRR was a success," said Lt. Col. Don Frew, GPS III Squadron Commander. "Lockheed Martin demonstrated to the government that the team is working to a solid requirements baseline and developing a mature design beyond what we normally see at a SRR. I want to thank the GPS III team for all their hard work and dedication."

The successful review demonstrated to the customer and user community the Lockheed Martin team's understanding of the inherent product development and technology maturity risks, how they will be met, and the program's readiness to continue to the GPS IIIB System Design Review.


GPS Satellite Artist's Rendering

"This important review effectively demonstrated our technology advancement and orderly, low-risk transition plan for meeting our customer's performance objectives," said John Frye, Lockheed Martin's manager of the GPS III Capability Insertion Program. "We are laser focused on executing to the baseline requirements in place for GPS IIIB while implementing the systems engineering processes necessary to accommodate change as GPS IIIB and GPS IIIC evolve."

The GPS IIIA satellites will deliver significant improvements over current GPS space vehicles, including a new international civil signal (L1C) and increased M-Code anti-jam power with full earth coverage for military users.

GPS IIIB will enable a cross-linked command and control architecture, allowing these GPS III vehicles to be updated from a single ground station instead of waiting for each satellite to orbit in view of a ground antenna. GPS IIIC will include a high-powered spot beam to deliver greater M-Code power for increased resistance to hostile jamming.

The team, which is progressing in the GPS IIIA Critical Design Review (CDR) phase of the program, has completed more than 80 percent of the planned CDRs and is well on its path to the overall space vehicle CDR in August, two months ahead of the planned schedule. Successful completion of the space vehicle CDR will allow the team to enter the production phase of the program.

FMI: www.lockheedmartin.com

Advertisement

More News

Airborne-NextGen 11.04.25: Anduril YFQ-44A, Merlin SOI 2, UAV Rulemaking Stalled

Also: Horizon Picks P&W PT6A, Army Buys 3 EagleNXT, First Hybrid-Electric Regional, Army Selects AEVEX Anduril Industries’ YFQ-44A Collaborative Combat Aircraft was flown>[...]

NTSB Prelim: Elmore Travis C Searey

While Flying North Along The Beach At About 300 Ft Above Ground Level, The Pilot Reported That The Engine RPM Dropped To About Idle On September 28, 2025, at 1126 eastern daylight >[...]

ANN's Daily Aero-Linx (11.03.25)

Aero Linx: European Association of Aviation Training and Educational Organisations (EATEO) Welcome to the “ European Association of Aviation Training and Education Organizati>[...]

ANN's Daily Aero-Term (11.03.25): On-Course Indication

On-Course Indication An indication on an instrument, which provides the pilot a visual means of determining that the aircraft is located on the centerline of a given navigational t>[...]

Aero-News: Quote of the Day (11.03.25)

“It also gives us the hard data we need to shape requirements, reduce risk, and ensure the CCA program delivers combat capability on a pace and scale that keeps us ahead of t>[...]