Emergency Runway Alterations Completed, But Questions Remain About Who Will Pay For Them
Emergency runway alterations have been completed at Columbia (MO) Regional Airport (KCOU), reopening the field to both GA and scheduled passenger service.
The airport had been closed a week ago Monday after airport officials say two of the three airlines that serve the airport suspended operations because of problems with the main runway. The crown of the main runway at the intersection with the secondary runway was causing rough landings, the airlines said. The crown was milled down over the course of the last week and the runway was repaved.
The problems came to light when the 6,500-foot main runway was closed on April 1 as the city began a $6 million project to refurbish and lengthen it. The crossing runway was rebuilt two years ago and lengthened to 5,500 feet, and was being used by the airlines while construction was being done on the main runway.
The milling and repaving project cost about $500,000, and The Columbia Daily Tribune reports that interim City Manager John Glascock said that the FAA would be required to pay for the repairs. But FAA regional spokeswoman Elizabeth Cory said in an email to the paper that federal funding is not automatic, and an AIP grant would not cover the full cost of the project.
In the email sent to the paper, Cory raised questions about Glascock's assumption that the FAA would pay for the modifications. But Glascock told the board of Regional Economic Development Inc. that the crown is necessary to drain water off the runway, and was built to federal specifications. Cory said that the FAA does not require drainage crowns to continue through a runway intersection. "FAA design standards call for designers to, 'Provide a smooth transition between intersecting pavement surfaces as well as adequate drainage of the intersection,'" she wrote.
She also questioned why the crown had suddenly become a problem 18 months after the project was complete.
The intersection was created when the secondary runway was extended. That runway had previously terminated where it joined the main runway at a skewed angle, according to the report.
More News
Instrument Approach Procedure (IAP) Charts Portray the aeronautical data which is required to execute an instrument approach to an airport. These charts depict the procedures, incl>[...]
“Our industry is approaching a 30-year innovation cycle, and we have less than 25 years to decarbonize aviation. We need to develop new methods to get net zero aerospace tech>[...]
Also: Girls in Aviation Day, B-29 Doc Heads 4 Chino, C-17 Tail Cone Detaches, Bulgaria Airshow Accident One of two private aircraft that launched from Apatity Airport near Murmansk>[...]
From 2021 (YouTube Version): We Were Blown Away At How Well The Nosewheel Was Adapted To The X Cub Airframe It should not be a secret to any one of you, that with thousands of hour>[...]
Also: Volato Nixed by Honda, New B-21 Bases, A-10 Unit Inactivated, Gogo/Airshare Boom Supersonic announced its demonstrator aircraft XB-1 successfully completed its third test fli>[...]