Wed, Jun 15, 2022

NASA Report Posits Moon Remains Distant

To Boldly Go—Over Budget

NASA intends to once again land human beings in the moon. The space agency intends, also, to bring Mars within the purview of human exploration.

These lofty and concomitant goals are largely dependent on the ongoing development of the Space Launch System (SLS)—a two-stage, heavy-lift rocket that will launch the Orion Multi-Purpose Crew Vehicle (Orion) into space.

Currently, NASA is developing two mobile launchers at its Kennedy Space Center in Florida. Each massive construct comprises a two-story base structure—the platform to support the SLS vehicle—and a tower equipped with connection lines; launch accessories; and a walkway for personnel, equipment, and astronauts. Once complete, the mobile launchers will facilitate the launch of various iterations of the integrated SLS/Orion system.

Construction of the first mobile launcher (ML-1) was completed in 2010. In 2019, NASA awarded a $383-million contract to Bechtel National, Inc.— the American engineering, procurement, construction, and project management company—to design, build, test, and commission the second mobile launcher (ML-2).

In March 2020, the NASA Office of Inspector General issued a report addressing the ongoing development of both mobile launchers. Subject report examined the extent to which the space agency is meeting cost, schedule, and performance goals for the ML-2 contract. The report brings to light shocking    overruns, and speaks to the inefficiencies, greed, profiteering, and breathtaking ineptitude with which U.S. Governmental programs are afflicted.

To wit.

NASA, by current estimates, will spend 2.5 times ($1-billion) more than initially planned for the ML-2 contract, and take delivery of the completed launcher 2.5 years later than scheduled.

As of May 2022, design work on the ML-2 remained incomplete.

Consequently, Bechtel officials do not expect actual construction of the launcher to begin until the first quarter of fiscal year 2023–at the earliest. When construction does begin, NASA expects unforeseen but inevitable technical challenges to engender further cost increases and delays. 

Once the new launcher is delivered, NASA testing requirements will see its operational debut pushed back to at least November, 2026. 

Compounding Bechtel’s projected cost increases and schedule delays, an ML-2 project analysis provided only a

3.9 percent confidence level that the nearly $1 billion cost and October 2025 delivery estimates were accurate. 

The Office of the Inspector General made a number of suggestions pertaining to better tracking spending, schedules, and keeping NASA and its contractors accountable for overruns, but the reports overall tenor suggested the goal of getting to the Moon by 2024 is no longer possible.

FMI: www.nasa.gov

Advertisement

More News

ANN's Daily Aero-Linx (05.04.24)

Aero Linx: JAARS Nearly 1.5 billion people, using more than 5,500 languages, do not have a full Bible in their first language. Many of these people live in the most remote parts of>[...]

NTSB Final Report: Quest Aircraft Co Inc Kodiak 100

'Airplane Bounced Twice On The Grass Runway, Resulting In The Nose Wheel Separating From The Airplane...' Analysis: The pilot reported, “upon touchdown, the plane jumped back>[...]

Aero-News: Quote of the Day (05.04.24)

"Burt is best known to the public for his historic designs of SpaceShipOne, Voyager, and GlobalFlyer, but for EAA members and aviation aficionados, his unique concepts began more t>[...]

Aero-News: Quote of the Day (05.05.24)

"Polaris Dawn, the first of the program’s three human spaceflight missions, is targeted to launch to orbit no earlier than summer 2024. During the five-day mission, the crew >[...]

Read/Watch/Listen... ANN Does It All

There Are SO Many Ways To Get YOUR Aero-News! It’s been a while since we have reminded everyone about all the ways we offer your daily dose of aviation news on-the-go...so he>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC