25% Of 'Releases' Now Complete
Boeing tells ANN that
it has reached a major milestone in the design of the all-new 787
Dreamliner. The team has completed 25 percent of the releases
required for the program. This means that one quarter of the pieces
of information to build parts and tools for assembly have been
completed and released to manufacturing organizations for
fabrication or procurement.
Releases are the formal documents -- digital models in the case
of the 787 program -- that allow purchases to be made, tools to be
developed and parts to be built.
"We have seen tremendous progress by our international partners
and the Boeing team working on the detailed design of this
airplane," said Mike Bair, vice president and general manager of
the 787 program.
"Twenty-five percent release signifies that the largest elements
-- like fuselage and wing skins -- are defined from the tooling
requirements to the specific raw material elements."
The 787, scheduled for delivery beginning in 2008, provides
passengers with a better flying experience and operators with a
more efficient commercial jetliner. Using 20 percent less fuel per
passenger than similarly sized airplanes, the 787 is designed for
the environment with lower emissions and quieter takeoffs and
landings. Inside the airplane, passengers will find cleaner air,
bigger windows, more stowage space and improved lighting. To date,
29 airlines have logged 393 orders and commitments worth more than
$55 billion at current list prices since the 787 launch in April
2004, making the Dreamliner the most successful commercial airplane
launch in history.
"There is still a lot of work to do as we continue to finalize
the design," said Bair. "I couldn't be more proud of our team. They
are bringing tremendous energy and expertise to this effort."
More News
Omnidirectional Approach Lighting System ODALS consists of seven omnidirectional flashing lights located in the approach area of a nonprecision runway. Five lights are located on t>[...]
"Polaris Dawn, the first of the program’s three human spaceflight missions, is targeted to launch to orbit no earlier than summer 2024. During the five-day mission, the crew >[...]
Also: 1800th E-Jet, Uncle Sam Sues For Landing Gear, Embraer Ag Plane, Textron Parts A friend of the family reported that Lt. Col. (Ret.) Richard Glenn Rutan flew west on Friday, M>[...]
Also: Virgin Galactic, B-29 Doc to Allentown, Erickson Fire-Fighters Bought, FAA Reauthorization After dealing with a big letdown after the unexpected decision by Skyreach to disco>[...]
“Our aircrews are trained and capable of rapidly shifting from operational missions to humanitarian roles. We planned to demonstrate how we, and our BORSTAR partners, respond>[...]