It's not exactly a
page-turner but a recently issued GAO report ANN is reading has us
a mite concerned... according to some of the data published
therein, the GAO found that, "It is uncertain whether the Air Force
will be able to acquire new satellites in time to maintain current
GPS service without interruption. If not, some military operations
and some civilian users could be adversely affected."
The GAO preface states that, "In recent years, the Air Force has
struggled to successfully build GPS satellites within cost and
schedule goals; it encountered significant technical problems that
still threaten its delivery schedule; and it struggled with a
different contractor. As a result, the current IIF satellite
program has overrun its original cost estimate by about $870
million and the launch of its first satellite has been delayed to
November 2009—almost 3 years late.
Additional GAO Considerations:
- ...while the Air Force is structuring the new GPS IIIA program
to prevent mistakes made on the IIF program, the Air Force is
aiming to deploy the next generation of GPS satellites 3 years
faster than the IIF satellites. GAO’s analysis found that
this schedule is optimistic, given the program’s late start,
past trends in space acquisitions, and challenges facing the new
contractor. Of particular concern is leadership for GPS
acquisition, as GAO and other studies have found the lack of a
single point of authority for space programs and frequent turnover
in program managers have hampered requirements setting, funding
stability, and resource allocation.
- If the Air Force does not meet its schedule goals for
development of GPS IIIA satellites, there will be an increased
likelihood that in 2010, as old satellites begin to fail, the
overall GPS constellation will fall below the number of satellites
required to provide the level of GPS service that the U.S.
government commits to. Such a gap in capability could have
wide-ranging impacts on all GPS users, though there are measures
the Air Force and others can take to plan for and minimize these
impacts.
The GA Report makes a recommendation that the Secretary of
Defense appoint a single authority to oversee development of GPS
space, ground control, and user equipment assets, to ensure they
are synchronized, well executed, and potential disruptions are
minimized. DOD reportedly concurred with GAO's
recommendations.
More News
Aero Linx: Model Aeronautical Association of Australia MAAA clubs are about fun flying, camaraderie and community. For over 75 years, the MAAA has been Australia’s largest fl>[...]
Touchdown Zone Lighting Two rows of transverse light bars located symmetrically about the runway centerline normally at 100 foot intervals. The basic system extends 3,000 feet alon>[...]
“Discovery and innovation are central to our mission at Virgin Galactic. We’re excited to build on our successful record of facilitating scientific experiments in subor>[...]
How To Get A Story On Aero-TV News/Feature Programming How do I submit a story idea or lead to Aero-TV? If you would like to submit a story idea or lead, please contact Jim Campbel>[...]
Student Pilot Reported That During Rotation, “All Of A Sudden The Back Of The Plane Kicked To The Right..." Analysis: The student pilot reported that during rotation, “>[...]