GAO Report Indicates NextGen Billions Over Budget | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.29.24

Airborne-Unlimited-04.23.24

Airborne-Unlimited-04.24.24 Airborne-FltTraining-04.25.24

Airborne-Unlimited-04.26.24

Sat, Feb 18, 2012

GAO Report Indicates NextGen Billions Over Budget

Half Of The Programs Are Experiencing Delays

In a review of 30 major ATC acquisition programs, all of which will contribute to the transition to NextGen, The Government Accountability Office (GAO) has found that costs for 11 of the 30 programs have increased from their initial estimates by a total of $4.2 billion, and 15 programs experienced delays. The 11 acquisitions that experienced cost increases account for over 60 percent of FAA’s total acquisition costs ($11 billion of $17.7 billion) for the 30 programs. The 15 acquisitions that experienced schedule delays, of which 10 also had cost increases, ranged from 2 months to more than 14 years and averaged 48 months.

In the executive summary of its Report to Congressional Committees, GAO says the cost increases and schedule delays occurred due to several factors, many of which have been longstanding challenges for FAA. Specifically, these have involved additional or unanticipated system requirements, insufficient stakeholder involvement (such as controllers’ input) throughout system development, underestimating the complexity of software development, and unanticipated events including funding shortfalls or work stoppages. GAO says that if they persist, these challenges will impede the implementation of NextGen, especially in light of the interdependencies among many acquisition programs, where cost increases or delays in one program can affect the costs and schedules of other programs.

For the four programs GAO selected to analyze in depth, GAO says the FAA is not consistently following the characteristics of high-quality cost estimates and scheduling best practices that GAO previously identified. Regarding cost estimates, GAO found that although all four of the programs generally provided well documented and comprehensive estimates, which are two of the four characteristics, no program fully met the two other characteristics.

Specifically, each program estimate was not credible because each lacked an independent cost estimate, which provides a check against FAA’s estimate and three programs lacked risk or uncertainty analysis. The estimates also lacked accuracy because they were not updated regularly or based on comparable programs. Regarding scheduling practices, most programs did not substantially or fully meet the majority of the 9 best practices GAO previously identified including developing a fully integrated master schedule of all program activities and performing a schedule risk analysis.

For example, without a schedule risk analysis, FAA is unable to predict, with any degree of confidence, if the estimated completion dates are realistic. FAA is implementing new processes and organizational changes to better manage acquisitions. However, by not consistently following the characteristics of high quality cost estimate and scheduling best practices, FAA cannot provide reasonable assurance to Congress and other stakeholders that NextGen and other ATC programs will avoid additional cost increases or schedule delays.

GAO was asked to determine how, if at all, costs and schedules of FAA ATC acquisitions programs, including those related to NextGen, have changed since they were first submitted to Congress, the reasons for any such changes, and the extent that selected ATC programs adhere to cost and schedule best practices. To do its work, GAO reviewed 30 programs and conducted cost and schedule analysis on four programs that had an approved baseline and were NextGen related. GAO reviewed acquisition documents and interviewed FAA officials.

It recommends that, to better estimate the cost and completion dates for major acquisitions, FAA should, among other things, require cost and schedule risk analysis, independent cost estimates and integrated master schedules. FAA did not comment on whether or not it agreed with the recommendations.

FMI: www.gao.gov

Advertisement

More News

Unfortunate... ANN/SportPlane Resource Guide Adds To Cautionary Advisories

The Industry Continues to be Rocked By Some Questionable Operations Recent investigations and a great deal of data has resulted in ANN’s SportPlane Resource Guide’s rep>[...]

ANN FAQ: Turn On Post Notifications

Make Sure You NEVER Miss A New Story From Aero-News Network Do you ever feel like you never see posts from a certain person or page on Facebook or Instagram? Here’s how you c>[...]

ANN's Daily Aero-Term (04.29.24): Visual Approach Slope Indicator (VASI)

Visual Approach Slope Indicator (VASI) An airport lighting facility providing vertical visual approach slope guidance to aircraft during approach to landing by radiating a directio>[...]

ANN's Daily Aero-Term (04.28.24): Airport Marking Aids

Airport Marking Aids Markings used on runway and taxiway surfaces to identify a specific runway, a runway threshold, a centerline, a hold line, etc. A runway should be marked in ac>[...]

ANN's Daily Aero-Linx (04.28.24)

Aero Linx: The Skyhawk Association The Skyhawk Association is a non-profit organization founded by former Skyhawk Pilots which is open to anyone with an affinity for the A-4 Skyhaw>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC