Record Rainfall Did Not Slow Down Runway Reconstruction
North Parallel Runway 12L/30R at
Minneapolis-St. Paul International Airport (MSP) reopened Thursday
evening, marking completion of a 20-year effort to replace aging
runway pavements at the facility.
Construction began August 18 on the $17.5 million project to
reconstruct the 3,800' center section of pavement, which dated back
to 1967. Since that time, air traffic has been redirected onto the
airport's three remaining runways, resulting in altered flight
patterns and noise distribution around the airport.
Once the FAA flight check of the runway's instrument landing
system is complete next week, runway use and the resulting flight
patterns around MSP will return to pre-construction conditions.
"Despite the challenges presented by near-record rainfall in
October, the runway is reopening according to schedule," said Jeff
Hamiel, Executive Director of the Metropolitan Airports Commission,
which owns and operates MSP and six general aviation airports.
"This was the last significant project in the $3.1 billion MSP 2010
expansion program. With the completion of that program, all
pre-existing runway pavement has been replaced and a new 8,000-foot
runway developed, providing ample airfield capacity for decades to
come."
The unusually cloudy, wet weather this month also contributed to
numerous flight delays and cancellations. With Runway 12L/30R out
of service, air traffic controllers had limited options for
directing air traffic in periods of low visibility, when aircraft
must be spaced further apart. Today's runway reopening gives air
traffic controllers' more options, reducing the severity of
potential delays. Once the FAA flight check is complete and Runway
12L/30R's instrument landing system is fully operational next week,
low ceilings (cloud cover) will have far less impact on flight
schedules and operational patterns.
Residents living under the approach and departure flight paths
for Runway 17/35 in Minneapolis and Runway 4/22 in St. Paul should
notice a reduction in aircraft overhead. Eagan residents might also
notice fewer aircraft taking off to the southeast from Runway
12R/30L. Residents of south Minneapolis who experienced a reduction
in aircraft overhead in recent weeks will notice a return to
pre-construction levels with flight patterns based on wind
direction and weather conditions.
More News
Very High Frequency The frequency band between 30 and 300 MHz. Portions of this band, 108 to 118 MHz, are used for certain NAVAIDs; 118 to 136 MHz are used for civil air/ground voi>[...]
Aero Linx: Aviation Suppliers Association Established February 25, 1993, the Aviation Suppliers Association (ASA), based in Washington, D.C., is a not-for-profit association, repre>[...]
Have A Story That NEEDS To Be Featured On Aero-News? Here’s How To Submit A Story To Our Team Some of the greatest new stories ANN has ever covered have been submitted by our>[...]
From 2021 (YouTube Version): Colorado Campus Offers aVariety Of Aerospace Entertainment And Education Wings over the Rockies Exploration of Flight is the second location for the Wi>[...]
Also: Paramotor Champ's, Electric Ultralight, ICON BK Update, Burt Rutan at Oshkosh! The Popular Rotorcraft Association is reaching out for help in rebuilding their private runway >[...]