AD: Honeywell International Inc. Turbofan Engines | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.01.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-Unlimited-04.11.24

Airborne-Unlimited-04.12.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Fri, Mar 22, 2019

AD: Honeywell International Inc. Turbofan Engines

AD NUMBER: 2019-05-07

PRODUCT: Certain Honeywell International Inc. (Honeywell) TFE731-20 and TFE731-40 turbofan engines.

ACTION: Final Rule.

SUMMARY: The FAA is superseding Airworthiness Directive (AD) 2017-20-01 for the engines listed above.

AD 2017-20-01 required removing the affected fan disk and replacing it with a fan disk eligible for installation. Since we issued AD 2017-20-01, the FAA determined that some turbofan engine models were omitted from the applicability of AD 2017-20-01.

This AD adds turbofan engine models to the applicability and removes the Honeywell TFE731-20 turbofan engine model from the applicability.

This AD requires removal of affected fan disks and replacement with parts eligible for installation.

This AD was prompted by two fan disks found with surface rollovers in the dovetail slot area.

DATES: This AD is effective April 25, 2019.

COST: The FAA estimates that this AD affects 61 engines installed on airplanes of U.S. registry. Operators may incur the following costs in order to comply with this AD:

  • Remove fan disk and send to Honeywell for inspection 8 work-hours × $85 per hour = $680 per engine.
  • Install reworked or new fan disk 26 work-hours × $85 per hour = $2,210 per engine

The FAA estimates the following costs to do any necessary fan disk replacements that would be required based on the results of the inspection. The FAA estimates that six engines will need this replacement:

  • Replace the non-serviceable disk with a new fan disk 1 work-hour × $85 per hour = $85. Parts: $50,000. Cost per engine: $50,085.
FMI: AD

Advertisement

More News

ANN's Daily Aero-Linx (04.15.24)

Aero Linx: International Flying Farmers IFF is a not-for-profit organization started in 1944 by farmers who were also private pilots. We have members all across the United States a>[...]

Classic Aero-TV: 'No Other Options' -- The Israeli Air Force's Danny Shapira

From 2017 (YouTube Version): Remembrances Of An Israeli Air Force Test Pilot Early in 2016, ANN contributor Maxine Scheer traveled to Israel, where she had the opportunity to sit d>[...]

Aero-News: Quote of the Day (04.15.24)

"We renegotiated what our debt restructuring is on a lot of our debts, mostly with the family. Those debts are going to be converted into equity..." Source: Excerpts from a short v>[...]

Airborne 04.16.24: RV Update, Affordable Flying Expo, Diamond Lil

Also: B-29 Superfortress Reunion, FAA Wants Controllers, Spirit Airlines Pulls Back, Gogo Galileo Van's Aircraft posted a short video recapping the goings-on around their reorganiz>[...]

ANN's Daily Aero-Term (04.16.24): Chart Supplement US

Chart Supplement US A flight information publication designed for use with appropriate IFR or VFR charts which contains data on all airports, seaplane bases, and heliports open to >[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC